Existing Likely

Horizon Compute Baobab Phase 1

Horizon Compute • United States of America • February 15, 2024
Total GPUs
1.0K
H100 Equiv
1.0K
Power
1.5 MW
FP16
1.0K PF

System Equivalents

This datacenter's 1.0K GPUs equal:

NVIDIA DGX H100
8 GPUs/system
128
NVIDIA HGX H100 (8-GPU)
8 GPUs/system
128
NVIDIA HGX H100 (4-GPU)
4 GPUs/system
256

Specifications

Primary GPUNVIDIA H100 SXM5 80GB
GPU Count1.0K
SectorPrivate

Additional Information

Since Q1 2024, we have already deployed two large-scale clusters (2000+ H100s)

Judging by their current offerings (March 2025), they have a 2k H100 cluster and a 1k H100 cluster, so I'm interpreting this as them saying that they had two 1k H100 clusters in Q1 2024