OpenAI Stargate Abilene Oracle OCI Supercluster Phase 3
Oracle • United States of America
H100 Equiv
5.1M
Power
2200.0 MW
FP16
5.0M PF
Specifications
| Location | 5502 Spinks Rd, Abilene, TX 79601 |
| Sector | Private |
Additional Information
"The initial plan here was a 1GW facility; SA now thinks it’s going to have a total of 2.2GW of power supplied and a critical IT capacity of 1.8GW." "SA estimates the campus will house a previously-announced 100k GB200 cluster, as well as a 200k GB300 cluster and a 400k VR200 cluster"
"That cluster is expected to be leased to Oracle, which in turn will lease it to Microsoft, who will rent it to OpenAI" Crusoe is involved in this FLOP/s figure is a very rough estimate based off some rumored specifications about chip performance
Related Datacenters
OpenAI Stargate Abilene Oracle OCI Supercluster Phase 2
758.0K H100 equiv
PlannedOracle OCI Supercluster B200s
298.0K H100 equiv
PlannedOpenAI Stargate Abilene Oracle OCI Supercluster Phase 1
252.7K H100 equiv
PlannedOracle OCI Supercluster H200s
65.5K H100 equiv
ExistingOracle OCI MI300x
21.6K H100 equiv